Namma Metro · Bengaluru
Namma Metro lines
Purple Line
OpenWhitefield – Challaghatta · 37 stations
Trains 5:00 AM – 11:05 PM, every 8 min at peak
Change atKR PuramMG RoadMajestic
Green Line
OpenMadavara – Silk Institute · 32 stations
Trains 5:00 AM – 11:05 PM, every 7 min at peak
Change atMajesticRV Road
Yellow Line
OpenRV Road – Bommasandra · 16 stations
Trains 6:00 AM – 11:55 PM, every 5.5 min at peak
Change atSilk BoardJayadevaRV Road
Lines coming later
Where each new line stands today, what happens next, and when trains could run. Targets are reported, not official, unless BMRCL has announced a date.
- Trial runs
Blue Line (airport line)
Central Silk Board – KR Puram – Hebbal – Airport
58.19 km · 29 stations · Silk Board–KR Puram section 19.75 km, 13 stations
- Awaiting approval
- Approved
- Construction
- Trials
- Open
- Where it stands
- Test trains run from Byappanahalli depot to Doddanekundi on the Outer Ring Road (since 10 Nov 2026). Civil work was about 72% done in August; signalling is the main job left.
- What happens next
- Finish the last stretch of track and the signalling, then the safety inspection by the Commissioner of Metro Rail Safety (not yet scheduled).
- When trains could run
- In three parts (below). The whole line, Silk Board to the airport, around March 2028. BMRCL targets, not official dates.
- Opens in parts
- 1Central Silk Board – KR Puram (Outer Ring Road)Phase 2A · 19.75 km · 13 stationsAround May 2027Trial runs
- 2Hebbal – Yelahanka – AirportPhase 2B, part 1 · 8 stations, Hebbal to KIAL TerminalsAround Sep 2027Under construction
- 3KR Puram – Nagawara – HebbalPhase 2B, part 2 · 8 stations, Kasturi Nagar to Kempapura; joins the two partsDec 2027 – Mar 2028Under construction
- Areas it serves
- HSR Layout, Agara, Bellandur, Marathahalli, Doddanekundi, KR Puram, Hebbal, Yelahanka, the airport
- Change to other lines at
- Silk Board (Yellow), KR Puram (Purple), Nagawara (Pink, later), Hebbal (Orange and Red, later)
Latest (10 Nov 2026): A test train reached Doddanekundi on the Outer Ring Road. Source
- Under construction
Pink Line underground
Dairy Circle – MG Road – Shivajinagar – Nagawara
13.76 km · 12 underground stations
- Awaiting approval
- Approved
- Construction
- Trials
- Open
- Where it stands
- The tunnels are built; platform screen doors and signalling are being installed and linked. The elevated first section, Kalena Agrahara–SG Palya, opened on 14 Nov 2026.
- What happens next
- Trial runs in the tunnels, then the safety inspection. No start of underground trials has been reported yet.
- When trains could run
- Around May 2027 (BMRCL target, not an official date).
- Areas it serves
- Lakkasandra, Langford Town, MG Road, Shivajinagar, Cantonment, Tannery Road, Nagawara
- Change to other lines at
- MG Road (Purple), Nagawara (Blue, later), Cantonment railway station
Latest (19 Oct 2026): BMRCL aimed to start running trains as far as Shivajinagar by November 2026; the opening target is May 2027. Source
- Approved
Orange Line (Phase 3)
JP Nagar 4th Phase – Mysuru Road – Peenya – Hebbal – Kempapura
32.15 km · 21–22 elevated stations · parts double-decker with a road flyover
- Awaiting approval
- Approved
- Construction
- Trials
- Open
- Where it stands
- Approved by the Union Cabinet in Aug 2024 (with the Grey Line, ₹15,611 crore). A ₹6,100 crore JICA loan was signed in Mar 2026. Civil tenders were invited in Jan 2026, but no contract is awarded yet: the double-decker design still needs the Centre’s clearance.
- What happens next
- The state aims to finish tendering and start work within six months (Minister Krishna Byre Gowda, Nov 2026). That is when work starts, not when trains run.
- When trains could run
- Not announced. The 2024 approval said 2029; newer reports point to 2031–32.
- Areas it serves
- Western Outer Ring Road: JP Nagar, Kamakya, Mysuru Road, Nagarbhavi, Sumanahalli, Peenya, Hebbal
- Change to other lines at
- JP Nagar 4th Phase (Pink), JP Nagar and Peenya (Green), Mysuru Road (Purple), Sumanahalli (Grey), Hebbal and Kempapura (Blue, Red)
Latest (11 Nov 2026): The government aims to complete tendering and begin work on the two Phase 3 lines within six months. Source
- Approved
Grey Line (Phase 3)
Hosahalli – Kadabagere, along Magadi Road
12.5 km · 9 elevated stations
- Awaiting approval
- Approved
- Construction
- Trials
- Open
- Where it stands
- Approved with the Orange Line in Aug 2024. Tenders to clear buildings along the route went out in 2026; the civil works tender has not been issued yet.
- What happens next
- Civil tender and start of work, aimed within six months (Minister Krishna Byre Gowda, Nov 2026).
- When trains could run
- Not announced.
- Areas it serves
- Magadi Road, from Hosahalli to Kadabagere
- Change to other lines at
- Hosahalli (Purple), Sumanahalli Cross (Orange)
Latest (11 Nov 2026): Same six-month aim for tendering and starting work on both Phase 3 lines. Source
- Awaiting approval
Red Line (Phase 3A)
Sarjapur – Koramangala – Dairy Circle – KR Circle – Hebbal
About 37.8 km (revised plan) · 27–28 stations · about 14 km underground
- Awaiting approval
- Approved
- Construction
- Trials
- Open
- Where it stands
- Karnataka approved it on 6 Dec 2024 (36.59 km, 28 stations). It went to the Centre in Jan 2025, came back over cost, and a revised plan was sent in 2026. The Centre says it is “under appraisal”.
- What happens next
- Approval by the Union Cabinet. If cleared, the state hopes to tender it and start work by the end of 2027.
- When trains could run
- Not announced; the revised plan targets 2033.
- Areas it serves
- Sarjapur Road, Agara, Koramangala, Dairy Circle, the city centre, Hebbal
- Change to other lines at
- Agara and Ibbaluru (Blue), Dairy Circle (Pink), KR Circle (Purple), Hebbal (Blue, Orange)
Latest (14 Nov 2026): The minister said the proposal has been waiting at the Centre for nearly 22 months. Source
Being studied, not approved: Madavara–Tumakuru, KR Puram–Hoskote, Challaghatta–Bidadi, Bommasandra–Attibele, Silk Institute–Harohalli and Kalena Agrahara–Kadugodi. Source (Sep 2026)
Checked 21 November 2026. Station counts and lengths are from project approvals and may change in the final design.