Updated 19 November 2026. The Bengaluru suburban rail is not running yet: of its 148 km, 0 km is open. Two lines, Mallige and Kanaka, are under construction with new contractors appointed on 29 October 2026. The other two, Sampige and Parijaata, have approved alignments but no construction. The official target is now December 2028 for the first line and March 2030 for the full network.
This guide covers the whole Bengaluru suburban rail project in one place: the four lines and where they run, every station on each line, why the project is years late, who is building it, and what is expected to open first. We update it whenever something official changes.
Bengaluru suburban rail at a glance
| What | The answer |
|---|---|
| Official name | Bengaluru Suburban Railway Project (BSRP) |
| Lines | 4, each named after a flower: Sampige, Mallige, Parijaata, Kanaka |
| Length | 148.17 km |
| Stations | 57 (K-RIDE’s count; stations shared by two lines are counted once) |
| Running today | 0 km |
| Approved cost | ₹15,767 crore |
| Built by | K-RIDE, a company owned 51% by the Government of Karnataka and 49% by the Ministry of Railways |
| Approved | October 2020, with a six-year deadline |
| First stretch expected | Chikkabanavara to Yeshwanthpur (about 7 km), targeted for December 2028 |
| Full network target | March 2030 |
The four lines
| Line | Route | Length | Stations | Status in November 2026 | Target |
|---|---|---|---|---|---|
| Sampige (Corridor 1) | KSR Bengaluru (Majestic) to Devanahalli, with a branch to the airport | 41.4 km | 15 | Alignment approved; surveys done; no construction contract yet | March 2030 |
| Mallige (Corridor 2) | Benniganahalli to Chikkabanavara | 25 km | 14 | Under construction; new contractor since October 2026 | December 2028 |
| Parijaata (Corridor 3) | Kengeri to Whitefield | 35.5 km | 14 | Alignment approved in 2026; soil testing to begin | March 2030 |
| Kanaka (Corridor 4) | Heelalige to Rajanukunte | 46 km | 19 | Under construction; new contractors for two of four packages | June 2029 |
The per-line station counts add up to 62, while K-RIDE gives 57 for the network. The difference is the stations where two lines meet, such as Yeshwanthpur and Yelahanka, which appear on both lists.

Sampige line: Majestic to Devanahalli and the airport
The Sampige line is the airport line. It starts at KSR Bengaluru City, next to Majestic metro station, runs north through Malleswaram and Yeshwanthpur, passes Lottegollahalli, Kodigehalli and Yelahanka, and ends at Devanahalli. A branch leaves the main line near Doddajala for the airport, with stops listed at the airport trumpet interchange, the terminal and the KIADB area.
Stations in order: KSR Bengaluru City, Srirampura (future), Malleswaram, Yeshwanthpur, Muthyal Nagar, Lottegollahalli, Kodigehalli, Judicial Layout, Yelahanka, Nitte Meenakshi, Bettahalasoor, Doddajala, Airport Trumpet, Airport Terminal, Airport KIADB, Devanahalli.
Where it stands: the state asked for work on this line to be held back because it runs close to the airport metro line. A revised alignment was approved jointly by the state and the Railways, and surveys and soil testing are complete, but no construction contract has been awarded. A €500 million KfW loan signed in December 2023 covers this line and Parijaata.
Mallige line: Benniganahalli to Chikkabanavara
The Mallige line is the shortest and the furthest along. From Benniganahalli on the east side it runs through Kasturi Nagar, Banaswadi, Nagawara and Hebbal, meets the Sampige line at Lottegollahalli and Yeshwanthpur, and continues north-west to Chikkabanavara.
Stations in order: Baiyappanahalli/Benniganahalli, Kasturi Nagar, Seva Nagar, Banaswadi, Kaveri Nagar (future), Nagawara, Kanaka Nagar, Hebbal, Lottegollahalli, Yeshwanthpur, Jalahalli (future), Shettyhalli, Myadarahalli, Chikkabanavara.
Where it stands: land acquisition for this line is reported complete and station contracts were awarded earlier. After L&T left in 2025, K-RIDE re-tendered the remaining civil work in three packages. Package 1 went to Cemindia Projects on 29 October 2026 for ₹665.61 crore, with 24 months to finish.
Parijaata line: Kengeri to Whitefield
The Parijaata line crosses the city west to east along the existing railway. It runs from Kengeri through Jnanabharathi and Nayandahalli to KSR Bengaluru City, then on through Bengaluru Cantonment and Bengaluru East to Baiyappanahalli, KR Puram, Hoodi and Whitefield (Kadugodi).
Stations in order: Kengeri, RV College (future), Jnanabharati, Nayandahalli, Krishnadevaraya, Jagjeevanram Nagar, KSR Bengaluru City, Kumara Park, Bengaluru Cantonment, Bengaluru East, Baiyappanahalli, Krishnarajapura, Hoodi, Whitefield.
Where it stands: this is the least advanced line. Its alignment was approved in 2026 and soil testing was due to begin; land acquisition is planned after the Sampige line.
Kanaka line: Heelalige to Rajanukunte
The Kanaka line is the longest. It runs up the east side of the city from Heelalige, near Electronic City and Bommasandra, through Carmelaram, Bellandur Road and Marathahalli to Benniganahalli, then north through Channasandra, Horamavu, Hennur, Thanisandra and Jakkur to Yelahanka and Rajanukunte.
Stations in order: Heelalige, Bommasandra (future), Singena Agrahara (future), Huskur, Ambedkar Nagar, Carmelaram, Bellandur Road, Marathahalli, Doddanekundi, Kaggadasapura, Benniganahalli, Channasandra, Horamavu, Hennur, Thanisandra, Hegde Nagar, Jakkur, Yelahanka, Muddanahalli, Rajanukunte.
Where it stands: on 29 October 2026 K-RIDE awarded two of the line’s four civil packages, worth ₹511 crore together: ₹342 crore to a joint venture of RNS Infrastructure and Gayatri Projects for the Benniganahalli to Jakkur section, with 24 months to finish, and ₹169 crore to RNS Infrastructure for a 13 km section between Heelalige and Bellandur. A Parliament reply in July 2026 said 43 of the 57 acres of private land needed had been acquired.
Where the suburban rail meets Namma Metro
Several suburban stops share a name or a neighbourhood with a Namma Metro station. K-RIDE has not published the walking links for each one, so read this table as “near the metro here”, not as a list of confirmed interchanges.
| Suburban stop | Suburban line | Nearby metro station | Metro line |
|---|---|---|---|
| KSR Bengaluru City | Sampige, Parijaata | Majestic | Purple and Green |
| Yeshwanthpur | Sampige, Mallige | Yeshwanthpur | Green |
| Kengeri | Parijaata | Kengeri | Purple |
| Jnanabharati | Parijaata | Jnanabharathi | Purple |
| Nayandahalli | Parijaata | Nayandahalli | Purple |
| Baiyappanahalli | Parijaata, Mallige | Baiyappanahalli | Purple |
| Benniganahalli | Mallige, Kanaka | Benniganahalli | Purple |
| Krishnarajapura | Parijaata | KR Puram | Purple; Blue under construction |
| Hoodi | Parijaata | Hoodi | Purple |
| Whitefield | Parijaata | Whitefield (Kadugodi) | Purple |
| Hebbal | Mallige | Hebbal | Blue, under construction |
| Nagawara | Mallige | Nagawara | Pink and Blue, under construction |
| Kodigehalli | Sampige | Kodigehalli | Blue, under construction |
| Yelahanka | Sampige, Kanaka | Yelahanka | Blue, under construction |
| Marathahalli | Kanaka | Marathahalli | Blue, under construction |
Until the suburban rail opens, the metro and buses are the way across the city. You can check any route on our trip planner, see the whole network on the Namma Metro map, or read our Pink Line guide and first and last train timings.
Timeline: from approval to today
- 7 October 2020: the Union government approves the four-corridor project at ₹15,767 crore, with a six-year deadline (October 2026).
- 20 June 2022: foundation stone laid, with a promise that the project would be ready in 40 months (October 2025).
- December 2023: the Kanaka line’s civil contract is signed with L&T, which already held the Mallige contract. A €500 million KfW loan for the Sampige and Parijaata lines is signed.
- March 2025: the Railway Minister tells the Lok Sabha that the transfer of state government land is “very slow” and that K-RIDE needs a full-time managing director.
- July 2025: L&T terminates its contracts for both lines, saying land was not handed over, and claims ₹505.89 crore. K-RIDE calls the termination illegal; the dispute goes to arbitration.
- October 2025: the 40-month promise expires with nothing open. K-RIDE begins re-tendering the Mallige line in three packages.
- December 2025: a full-time managing director is appointed. At a review on 31 December, K-RIDE presents new targets: December 2028, June 2029 and March 2030.
- May 2026: Integral Coach Factory, Chennai, gets a ₹1,513.75 crore contract for 153 air-conditioned coaches: 51 three-coach trains for the Mallige and Kanaka lines.
- October 2026: the original six-year deadline passes with nothing open. On 29 October, new civil contracts worth about ₹1,176 crore are awarded for the Mallige and Kanaka lines.
Why the Bengaluru suburban rail is late
The delay has several causes, and they are on the record.
- Land. In a written reply in the Lok Sabha in March 2025, the Railway Minister said Indian Railways had transferred its land to K-RIDE but “progress of transferring of State Government land is very slow”. In April 2026 only 7.8 of the 57 acres of private land for the Kanaka line had been acquired; by July 2026 that was 43 acres.
- No full-time head. The same reply said K-RIDE was run by a part-time managing director and needed a full-time one who knew railway technology. One was appointed in December 2025.
- The contractor left. L&T held the civil contracts for both lines under construction and terminated them in July 2025, citing land that was not handed over. Re-tendering took more than a year.
- The airport line was held back. The state asked for the Sampige line to be deferred because it runs near the airport metro line, so its alignment was settled only in 2026.
- Trains were ordered late. A plan to lease trains through a private partner fell through. The order went to ICF in 2026, and a September 2026 report put the first trains at least three years away: about two years to build and one to test.
That last point sits awkwardly with the December 2028 target for the Mallige line. K-RIDE has not explained how the two fit together, so we treat every date here as a target, not an opening date.
Who is building it, and who pays
The project is built by Rail Infrastructure Development Company (Karnataka) Limited, known as K-RIDE. Karnataka owns 51% and the Ministry of Railways 49%. The cost is shared: 20% from the Union government, 20% from the state and 60% from loans.
| Work | Who | Value | Status |
|---|---|---|---|
| Mallige line, civil package 1 | Cemindia Projects | ₹665.61 crore | Awarded 29 October 2026; 24 months |
| Kanaka line, Benniganahalli to Jakkur | RNS Infrastructure and Gayatri Projects (joint venture) | ₹342 crore | Awarded 29 October 2026; 24 months |
| Kanaka line, Heelalige to Bellandur | RNS Infrastructure | ₹169 crore | Awarded 29 October 2026 |
| Kanaka line, two more civil packages | Not yet awarded | To be tendered | |
| Trains: 51 three-coach AC sets | Integral Coach Factory, Chennai | ₹1,513.75 crore | Contract May 2026; at least three years to delivery |
| Earlier civil contracts, both lines | Larsen & Toubro | Terminated by L&T in July 2025; in arbitration |
What opens first, and when
The first stretch expected to carry passengers is on the Mallige line: Chikkabanavara to Yeshwanthpur, about 7 km. Earlier targets for this stretch, including December 2025, were missed. The current target for the Mallige line is December 2028.

| Line | Target |
|---|---|
| Mallige (Benniganahalli to Chikkabanavara) | December 2028 |
| Kanaka (Heelalige to Rajanukunte) | June 2029 |
| Sampige (Majestic to Devanahalli and the airport) | March 2030 |
| Parijaata (Kengeri to Whitefield) | March 2030 |
K-RIDE has said the lines will not all open on the same day. With the airport line and the Kengeri to Whitefield line still without construction contracts, March 2030 is the date most likely to move.
Frequently asked questions about the Bengaluru suburban rail
Is the Bengaluru suburban rail running?
No. As of November 2026 none of the 148 km is open. Two lines, Mallige and Kanaka, are under construction, and the other two have not started. The first passenger stretch, Chikkabanavara to Yeshwanthpur, is targeted for December 2028.
When will the Bengaluru suburban rail open?
The official targets are December 2028 for the Mallige line, June 2029 for the Kanaka line and March 2030 for the Sampige and Parijaata lines. These are targets, not confirmed dates; the original deadlines of October 2025 and October 2026 were both missed.
How many lines and stations does the Bengaluru suburban rail have?
Four lines covering 148 km: Sampige (41 km, 15 stations), Mallige (25 km, 14 stations), Parijaata (35 km, 14 stations) and Kanaka (46 km, 19 stations). K-RIDE counts 57 stations in all, because stations shared by two lines are counted once.
Why is the Bengaluru suburban rail delayed?
The Railway Ministry told Parliament in 2025 that state land transfer was “very slow” and that K-RIDE had no full-time managing director. Contractor L&T then left both lines under construction in July 2025. New contractors were appointed in October 2026.
Will the suburban rail go to Bengaluru airport?
Yes, on paper. The Sampige line from KSR Bengaluru (Majestic) to Devanahalli has a branch to the airport. Its alignment is approved, but construction has not started and its target is March 2030.
Which suburban rail line will open first?
The Mallige line, starting with about 7 km between Chikkabanavara and Yeshwanthpur. Its target is December 2028. A new contractor, Cemindia Projects, was appointed for its remaining civil work on 29 October 2026 with 24 months to finish.
Sources
Swarajya, 19 March 2025: the Railway Minister’s Lok Sabha reply on land, the managing director, cost sharing and K-RIDE’s ownership.
The Week, 2 August 2025 and
Deccan Herald: L&T’s termination, its claim and K-RIDE’s response.
NewsFirst Prime, 20 January 2026 and
Metro Rail Today, 11 February 2026: the revised targets for each line.
NewsFirst Prime, 7 April 2026: land status and the managing director’s appointment.
Swarajya, 18 May 2026: the Railway Minister’s update on all four corridors.
Railway Gazette International, 5 June 2026 and
NewsFirst Prime, 2 September 2026: the train order, line lengths and station counts.
Deccan Herald and
News Karnataka, 1 November 2026: the Kanaka line contracts and land figures.
The Metro Rail Guy: station lists for each line (as of June 2025).
K-RIDE: the project’s 57-station count.
Facts checked on 19 November 2026 against Parliament replies, K-RIDE statements and the news reports listed above. Lengths are rounded and some stations on the lists are marked “future”. Target dates are official targets, not confirmed openings; we will update this page when they change. Maps are StationSeekers drawings that follow the existing railway; line colours are ours, not official.
Make commuting simple.
Find your nearest station, plan a door-to-door metro trip, and check fares and last trains before you leave.




